|
 |
Judgement
was handed down on Friday 28/03/03 in the much-vaunted IR35
High Court case of Synaptek v IR, also known
as the Stutchbury case. Mr Stutchbury had originally been ruled
to be within IR35 at the General Commissioners and had appealed
to the High Court to contest this view. The Court found in favour
of the Revenue, confirming the original ruling that IR35 did
apply to the arrangements between Mr Stutchbury and his end
client, EDS.
The contractual arrangement was complicated by the fact that
there was no direct contractual relationship between Mr Stutchbury’s
company Synaptek and EDS, as Synaptek’s agreement to provide
services was made with an agency, NESCO. EDS was itself providing
services to the Benefits Agency at the Inland Revenue as successor
to the Government IT Services Agency, which was the end client
of Synaptek and NESCO during a previous period. |
|
Mr
Justice Hart emphasised throughout that it is not for him to
decide the deemed employment status of
Mr Stutchbury, merely to decide whether the General Commissioners
had erred in law in their original decision. He has not therefore
given any additional guidance as to the relative weight of the
different status indicators, but it will be useful for contractors
to be aware of some of the salient facts about the engagement.
The Judge summarised the factors in this case that pointed to
a “contract
for services” (deemed self-employment) as follows: |
 |
· Synaptek/Mr Stutchbury was “in business
on its own account”. This was demonstrated by substantial
investment in the company; a varied client base both historically
and during the currency of the EDS engagement; Synaptek had in
the past engaged a total of four to five employees. |
· EDS
only had “limited
control” over ‘how’ the
work was to be performed, or specifically ‘when’. The
Judge did not particularly refer to the limited control as to ‘where’ the
work was performed – this was one initial location subject
to change by agreement with the agency. |
· Contract contained a “right of substitution”.
This was stated as a factor for deemed self-employment even though
both parties had accepted that Mr Stutchbury personally performed
services. The actual clause in the agreement was negatively worded
and required the unqualified consent of EDS. Mr Justice Hart stated: “the
effect of the contract is that, unless and until agreed otherwise,
the services do have to be performed personally by Mr Stutchbury”. |
· Synaptek was “responsible for training” for
its representatives and provision of computer facilities at its
own premises. |
| · Intellectual
Property Rights had to be assigned to EDS, rather than already
vesting in EDS as
would be the case for EDS employees. |
| · Synaptek was required to maintain “professional
indemnity insurance”. |
| · Synaptek/Mr Stutchbury had “flexibility
of hours worked”. |
| · Synaptek/Mr Stutchbury brought
in its “own reference books” whilst on-site. This was
stated as a factor for deemed self-employment even though Mr Stutchbury
did not use any of his (or Synaptek’s) equipment on-site
specifically to perform the work. |
 |
Conversely,
the Judge summarised the factors in this case that pointed
to a “contract of services” (deemed
employment) as follows: |
 |
| · Minimum 37.5 hours per week
required, broadly equivalent to a “normal working week”. |
| · The
only risk borne by Synaptek/Mr Stutchbury was the risk of insolvency
of the agency or EDS. This
point is of interest as there are other facts that suggest that
there was more risk than was identified by the Judge. For example
the Agreement could be terminated with immediate effect if the
services were not performed to the satisfaction of EDS. |
| · The duration was for a “fixed
period” of six months rather than being linked to completion
of a particular project. This emphasises the need for a genuinely
project-based contract rather than merely ‘time and skill-set’. |
| · Mr Stutchbury worked “alongside
EDS employees” and was sufficiently integrated to have an
EDS line manager. |
| · The contract required “compliance
with all instructions” of EDS. It is important to note that
there was no subsequent mention of the other parts of the respective
clause in the Agreement, which also referred to on-site rules,
procedures, policies etc of EDS. |
 |
It is interesting that, although mutuality
of obligations was not stated as a specific factor for or against
a contract for services, it was examined in the judgement. The
particular clause in the agreement that had been relied on by Synaptek
to exclude mutuality of obligation read as follows: |
|
“6.4:
In any event no payment will be made by NESCO to the Company
in respect of any contractual period
not actually worked including notice periods.” |
|
The
Judge contested that the clause served merely to emphasise
that payment is dependent on actual work having
been done, and does not detract from a separate clause (4.3)
requiring the agency (and through the ‘hypothetical contract’ requiring
EDS) “to allocate work to the Company”. The Judge
also highlighted the often-misunderstood key distinction between
mutuality
of obligation during the currency of the contract, and mutuality
of obligation between contracts. The Judge effectively considered
that there must be an obligation on the agency/EDS to provide
work during the currency of the contract, as otherwise the various
termination
provisions could serve no purpose. |
|
The
decision is a blow to many contractors who may believe that
they are outside the scope of IR35 and once
again highlights the importance of the actual arrangements being
properly reflected in appropriate contract terms. The decision
confirms the importance of properly drafted ‘project-based’ contracts
as a means of legitimately avoiding IR35. It also counters advice
given by some advisors that all that is required is for the contractor
to be ‘in business on his own account’ - a theory
effectively rejected by the Court. The underlying principle remains
true that,
given the complexities involved, the only security a contractor
can gain is to have proper legal advice from the outset on how
to operate, matched with a proper commercial agreement. There
is no simple shortcut around IR35, and the current lure in some
quarters
for contractors to seek comfort from completing a simple question
and answer form is simplistic and dangerous in the extreme. |
|
|
| Article Written 01/04/03 |
  |
 |